Quarterly Report to the Harry Reid Center
UCCSN-DOE Cooperative Agreement
Task 12: Seismic Monitoring
PI: James N. Brune
UNR Seismological Laboratory
Report Period: 04/01/2001 – 06/30/2001
Progress:
During this reporting period (Jan-Mar 2001), we have maintained
seismic operations under the QA procedures which have been established with the
HRC. Data collection has been above 98%
overall.
We have submitted the FY98-99 seismicity report, including data
submittals to the TDMS of the two major datasets of the report. We have completed a draft of the FY00
seismicity report and submitted it to a technical reviewer. Preliminary data submittals of the two major
datasets were made. These are non-Q,
pending technical review of the report.
At the end of June, we have analyzed the earthquakes in the YM
vicinity through approximately June 2, thus leaving a 28-day delay. This is an increase of 14 days over the
delay reported at the end of March.
Seismic activity in the YM vicinity has remained unusually low during
this reporting period.
We have purchased a DVD-ROM recording system in this past
quarter. Procedures for making DVD’s
have been devised, and our first DVD submittals to the RPC will occur about
July 1.
The software qualification effort for MLCALC completed, except for
acceptance by the Software Configuration Management group. Issues with 4 previously qualified software
packages were raised by the SCM, and we have responded to those.
An audit was conducted on our task by DOE in the week of May 21. We were issued one Deficiency Report, for
which a response has already been given.
Problems:
We are still awaiting the final environmental record of decision
from Death Valley National Park regarding the three stations to be installed in
the park.
Another revision to AP-SI.1Q (Software Management) during the past
quarter has caused us delay in software qualification efforts. The response of the SCM group is seemingly
slower than at any previous time, and a recent “standdown” on software
activity, although it is not supposed to affect us, is apparently slowing SCM.
We have been unable to renew the “Q” badge status of one of our
technicians, John Torrisi. His Q badge
was formerly obtained via the USGS, but they have stated they are unwilling to
support us on this anymore. Requests
for DOE personnel to intervene have been unsuccessful. Lack of a Q badge will eventually impact our
ability to maintain the seismic network.
Status of Funds:
We anticipate a zero balance on 6/30/2001. All equipment purchases have been made, and
final accounting by the UNR system should occur sometime in July.
Plans:
We plan to reduce our backlog to < 10 days of seismic event
processing during the next quarter. Our
student worker will have more time to give this effort, and the lab is
completing the hiring process for a permanent position to do this type of work.
Pending receipt of review comments, we will finalize and submit
the FY00 seismicity report and submit the final datasets to the TDMS.
We will resolve the one Deficiency Report issued from our May audit.