Quarterly Report to the Harry Reid Center
UCCSN-DOE Cooperative Agreement
Task 12: Seismic Monitoring
PI: James N. Brune
UNR Seismological Laboratory
Report Period: 10/01/2002 – 12/31/2002
Progress:
During this reporting period (Oct.-Dec. 2002), we have maintained
seismic operations with 30 real-time SGBDSN stations under the QA procedures
that have been established with the HRC.
Data collection has been above 99.7% overall.
The FY01 seismicity report, finished in June, is waiting only for
completion of a Technical Assessment of two datasets (Oct.-Dec. 1992 and
Jan.-Sep. 1995 earthquake catalogs) used in preparation of that report. This assessment has been reviewed and is in
final preparation for submittal.
At the end of this quarter, we have completed analyzing the
earthquakes in the YM vicinity through September 17. Completion of analysis on a delayed basis is acceptable because
the entire set of station triggers is reviewed within 2-3 days and because all
events larger than roughly M 2 are always analyzed within these 2-3 days. The backlog is still due to the occurrence
of the M 4.4 earthquake near Little Skull Mountain on June 14. Over 2500 aftershocks of this event have
already been located through September 17.
This number alone is greater than the average number of events per year
since the SGBDSN started.
The accelerometers for the three boreholes on the pad of the
proposed Waste Handling Building, delivered in early October, were returned to
Kinemetrics for correction of sensor outputs.
Meanwhile we then completed the testing of the Q330 recording units
according to IPR-021. We also received
on-site training from Kinemetrics on the configuration of the Q330’s on
December 12-13. Preliminary setup for
the testing of the sensors according to IPR-021 has been done. At the three boreholes, the concrete pads
were constructed by Bechtel; and we have installed the solar panels and
batteries on the pads at all three sites.
We have had discussions with the RPC in this quarter concerning
the updating of their media that contain seismic data. They are currently developing a sole-source
RFP for us to continue work on preserving the seismic data collected in the
southern Great Basin since 1978. Also,
in this past quarter, we have completed the organization of a large waveform
dataset for all the events located with the SGBDSN from 1995-1999 (roughly
10000 earthquakes). This dataset will
be submitted on DVD media to the HRC TDA in early January.
An organizational meeting on the kappa project was held at UNR on
December 16. The scientific aims were
set at this meeting, and a discussion of all QA impacts on the work was
held. An IPR for the field work is in
initial stages of drafting.
Problems:
The backlog of events to be analyzed following the June 14, 2002,
earthquake has grown to roughly three months.
This can be gradually reduced, provided no more significant earthquakes
occur in the network. However, this has
delayed our processing of the final catalog of earthquakes for FY2002.
The delay in acquiring the instruments for the tunnel and for the
boreholes has pushed out the finish dates for these subtasks. The complexity of the Kinemetrics Q330
recording units has also caused delays due to a significant learning curve.
Status of Funds:
We have expended approximately $253K of our $1336 funding through
December 31. This is only 19% of the
funds, while a straight-line projection would be 33%. We are thus significantly under-running. The reasons for this are largely due to
three unfilled job positions (computer system administrator, seismic
technician, and a post-doc). The
protracted nature of job searches within the UNR system has delayed our
hiring. We intend to have at least two
of the positions filled by the end of January.
Another reason for the under-run is that the subcontract to UCSD for
support on the kappa project is being put in place just now in early January.
Plans:
We will complete the hiring of three more personnel in this
quarter: computer system administrator, field technician, and a post-doc. These positions are key factors in
completing our workscope in FY03.
We will complete the installation of surface recording equipment
at the three WHB pad boreholes in January, followed by installation of the
downhole accelerometers later in the quarter.
The equipment for three ESF sites will installed and the Antelope
recording setup will be placed in the “data shack” on the north portal in the
Jan.-Mar. quarter.
We will deliver the long-delayed FY01 seismicity report in January and begin work on the FY02 report also in January.
We will work on the numerous subtasks for which we have been funded in FY03, notably attenuation, stress-drop, and focal-mechanism efforts.