Quarterly Report to the Harry Reid Center
UCCSN-DOE Cooperative Agreement
Task 12: Seismic Monitoring
PI: James N. Brune
UNR Seismological Laboratory
Report Period: 01/01/2003 – 03/31/2003
Progress:
During this reporting period (Jan.-Mar. 2003), we have maintained
seismic operations with 30 real-time SGBDSN stations under the QA procedures
that have been established with the HRC.
Network uptime has been 97.1% overall.
A few winter-storm icing situations and some hardware failures at the
lab have resulted in downtimes. The
nine untelemetered strong-motion stations were visited in this past quarter for
maintenance and data downloading.
The FY02 seismicity report has been drafted and is undergoing
internal review. It contains a
substantial section on the M 4.4 earthquake on 14 June 2002 at Little Skull
Mountain.
At the end of this quarter, we have completed analyzing the
earthquakes in the YM vicinity through November 12. Approximately 45 days of 2003 are also complete. The entire set of station triggers is
reviewed within 2-3 days and all events larger than roughly M 2 are always
analyzed within 2-3 days also. The
backlog is still due to the occurrence of the M 4.4 earthquake near Little
Skull Mountain on June 14, 2003. Over
2900 aftershocks of this event ended up in the SGBDSN catalog through the end
of FY02. This number alone is greater
than the average number of events per year since the SGBDSN started.
The accelerometers for the three boreholes on the pad of the
proposed Waste Handling Building were installed in two separate efforts,
January 21-22 and March 18-19. There
are 9 3-component sensors for a total of 27 channels of data that is being
collected onsite by the Antelope software system and also in onsite disks as
backup. Daily QC checks of the data are
being done by remote login. A problem
with the onsite calibration is not yet solved and has required returning one
set of the instrumentation to the lab for diagnosis.
RefTek instruments that were earmarked for the ESF had to be returned
to the manufacturer to fix a firmware bug.
The firmware fix is necessary to receive correct timing information from
the True-Time GPS receiver that is installed outside of the ESF along the fiber
connection. We have requested that
small pads be constructed at the ECRB Niche 5 location and at the strainmeter
location. The decision on the
installation at Niche 5 is dependent on UC Berkeley activities in the
alcove. Fiber connections to hardware
that provide accurate time to the ESF units are being completed by the TCO.
We have submitted the dataset for all the events located with the
SGBDSN from 1995-1999 (roughly 10,000 earthquakes). This was submitted on DVD media to the HRC TDA in January. QA activity to qualify old datasets
consisting of 1992 and 1995 analog network hypocenter lists has been completed.
Data qualification efforts are proceeding for the project to
reevaluate kappa. Borehole seismic data
from 1997-1998 portable recorders and portable weak-motion data at TerraTek
strong-motion sites are top priorities.
Functional definition and programming are nearly done for software to
measure kappa and present results. The
IPR governing the field procedures for refraction microtremor surveys in
support of the kappa study was submitted for review and is now being rewritten
to address the reviewers’ comments.
Fieldwork is on hold until the environmental standdown for YM work is
cancelled.
In January we were able to complete the hiring for our system
administrator slot. There was a good
field of candidates and we were able to hire a very talented individual.
Problems:
The backlog of events to be analyzed following the June 14, 2002,
earthquake continues at roughly three months.
We have been working to reduce this backlog, making slight headway this
past quarter.
The environmental standdown is a serious impediment to our
fieldwork in support of the kappa investigation.
Status of Funds:
We have expended approximately $653K of our 9-month funding of
$1336K through March 31. This is only
49% of the funds, while a straight-line projection would be 67%. We are thus significantly
under-running. The reasons for this are
largely due to two unfilled job positions (new seismic technician, and a new
post-doc). The difficulty of attracting
suitable candidates has hampered these searches. Also, fieldwork originally planned in support of the kappa
project has been postponed repeatedly.
Plans:
Approval will be sought for construction plans at Alice Ridge and
at Skull Mountain for telemetry relay stations. These relay stations will allow us to transmit the WHB borehole
data and the ESF data to Reno. They are
the first facilities in a planned upgrade of the entire seismic monitoring
network to IP packet transmission.
Contingent on not having a shutdown of ESF operations and also on
having the instruments returned from the manufacturer, the seismic equipment
for three ESF sites will be installed in the current quarter and data from
these sensors will be collected by the Antelope software system at the TCO data
shack near the ESF north portal.
We will have the FY02 seismicity report reviewed in April and deliver it by the end of May. The kappa report will be ready for review in May and will be delivered in June.
QA of the kappa estimation code will be starting in mid-April. Microtremor surveys in support of the kappa project will begin in earnest after the mid-May end of academic UNR semester.
Work on the focal-mechanism program will begin in this quarter; our Post-Doc (to be hired) will help on this project as it matures.