Quarterly Report to the Harry Reid Center
UCCSN-DOE Cooperative Agreement
Task ORD-FY04-006: Seismic Monitoring
PI: James N. Brune
UNR Seismological Laboratory
Report Period: 07/01/2004 – 09/30/2004
Progress:
During this reporting period (Jul.-Sep. 2004), we have maintained
seismic operations with 29 real-time SGBDSN stations under the QA procedures
that have been established with the HRC.
Network uptime has been 99.9% over the three months.
As of this reporting date (10/07/2004), we have nearly completed
analysis of the earthquakes in the YM vicinity through September 30. Aftershocks
of an M 5.5 earthquake near
The draft of the report on the FY2003 seismic activity in the
vicinity of
A draft report on the preliminary observations with accelerometers
at three boreholes on the ESF pad has been modified to resolve all comments. An assessment of part of the waveform data
has been undertaken to obtain a Q stamp for it.
A paper on precarious rocks and Little Skull Mt. earthquake
simulations has been accepted for publication in the Bulletin of the Seismological
Society of America.
The SDR for the kappa determination software has been completed. The SDR for the program SEISOPTREMI is in
progress. Software qualification reports
((LLR) on four programs (REF2ORB, DBPICK, DBOC2, CALIB) have been submitted –
three are approved and one is pending.
Two other software qualification exercises have been started for
HYPOINVERSE and MLCALC; these are high-level programs.
Installation of the ESF seismic instrumentation at three locations
in the tunnel (Alcove 5, ECRB Niche 5, and at the east end of the strainmeter) is complete.
Data is being collected in real-time from both weak-motion and
strong-motion sensors at these sites now.
Factors for converting digital counts to true ground motion have been
determined.
Equipment for three seismic sites over the ESF has been ordered,
as well as upgrade equipment for 2 of the older
strong-motion stations which will then be enabled for telemetry.
Installation of power and telemetry equipment at UZ16, Fran Ridge,
and at the TCO data shack is complete as of this date (10/07/2004).
Problems:
Multiple delays in the work orders for concrete pouring at the TCO
data shack for a telemetry antenna mast and at UZ-16 for solar panels and the
antenna mast delayed our installations there until October.
The kappa software QA effort is behind schedule and has impacted
our delivery schedule for this report (originally 9/30/2004).
Although not final, it is important to point out that plans for a
tunnel powerdown and closure would severely impact
our data collection in the tunnel.
Status of Funds:
As of 9/30/2004, we had expended $1,642K on Task 6. This represents 95% of the total
appropriated, $1,727K for FY2004. We
purposely held over some funds to address the usual start-of-FY funding delays,
but will exhaust those in October.
Plans:
In the next quarter (Oct.-Dec.) we plan to request
approval for the 3 sites above the 3 ESF tunnel installations. We plan to install the recording equipment at
UZ-16, hook up geophones in that well, and conduct a shakedown of the recording
system. We plan to occupy the small
building on top of
We will complete and deliver both the report on the FY2003 seismicity in the vicinity of YM and the report on preliminary findings at the borehole accelerometer array on the ESF pad.
We intend to finish the software qualification for the two programs needed in the kappa project this coming quarter and produce the final kappa computations. We will complete as many ReMi surveys as possible on permitted sites before the end of the year.
Several abstracts related to our