Quarterly Report to the Harry Reid Center
UCCSN-DOE Cooperative Agreement
Task ORD-FY04-006: Seismic Monitoring
PI: James N. Brune
UNR Seismological Laboratory
Report Period: 01/01/2005 – 03/31/2005
Progress:
During this reporting period (Jan.-Mar. 2005), we have maintained
seismic operations with 29 real-time SGBDSN stations under the QA procedures
that have been established with the HRC.
Network uptime has been 99.9% over the three months (except see below). In addition, we have maintained QA data collection
from 9 accelerometers in 3 boreholes on the ESF pad and from 3
acceleometer/seismometer installations in the ESF itself.
Earthquake activity in the network has been notably light during
this reporting period, and we are impacted somewhat by the loss of data from 9
stations due to the continuing power outage at
Locations have been finalized for the FY2004 earthquake catalog,
and a high-level software qualification SQR is being completed to validate program
MLCALC,V3.0 so that we can compute the final magnitudes.
Kappa software QA is proceeding slowly. Validation testing has been completed and minor issues related to it have been resolved. Final documents are being drawn together for resubmission and approval.
Data telemetry through the
The data acquisition and software systems developed for borehole
UZ-16 are being bench tested. The unit
successfully transmits 64 channels of 200 sps time-stamped data via TCP/IP to
an Antelope system. Thus, we have tested
the software systems that will be employed at the borehole and ESF pad. Next we will test data communications from a
remote location using seismic sensors to confirm system performance prior
installation at UZ16.
Strong-motion data was submitted to the TDMS including system
check results. No significant
earthquakes occurred in the YM area during the reporting period.
Problems:
The mode of delayed funding for the start of FY2005 has impacted
us greatly. We just received the full
funding allocation on March 31. All
equipment purchases for FY2005 have been delayed, pending the full allocation.
The kappa software QA effort is behind schedule and has impacted
our delivery schedule for this report (originally 9/30/2004).
The data assessment exercise for the borehole accelerometer report
has caused this report to be delayed.
The assessment is now only waiting for a signature from one of the
assessment team.
The power outage at
Environmental permits have been requested for the 3 sites above the 3 ESF tunnel installations but have
not been approved. We have already
purchased the equipment for these sites.
Status of Funds:
As of 03/31/2004, we had expended $669K of FY2005 funds on Task 6,
out of a total FY2005 allocation of $1,705K.
This is a substantial underrun at this time, but is largely explained by
the delay of equipment purchases, amounting to approximately $200K in our
FY2005 budget.
Plans:
We plan to install the recording equipment at UZ-16, hook up geophones in that well, and start continuous recording of 63 channels. We will transmit the real-time data to the TCO data trailer where it will be stored in a 10- to 20-day online buffer area.
We will complete and deliver the report on preliminary findings at the borehole accelerometer array on the ESF pad; this report has been held up for a technical data assessment which is now resolved.
We will finish the preparation of the FY2004 earthquake
catalog for the
We will purchase the equipment itemized on our FY2005 budget and start the recorder replacement cycle at the 29 stations of the permanent network, perform the upgrade of a few independent strong-motion sites to telemetered recording, and install new computers in our seismic analysis room.