1) Plan of Work:
United States Geological Survey Seismic Imaging Study in the Cities of Reno and
Sparks, Nevada, June 2009
Version May 21, 2009, Contractor: John N. Louie, Prof. of Geophysics, Nevada Seismological
Laboratory, University of Nevada, Reno; louie@seismo.unr.edu,
office 775-784-4219, fax 784-4165, cell 229-3835
To better understand earthquake hazards in the City of Reno and along the Reno-Carson City Urban Corridor, the United States Geological Survey (USGS) is preparing to undertake a high-resolution, non-invasive, seismic imaging study of the Truckee Meadows Valley. The purpose of this investigation is to get a clearer picture of subsurface soil and rock layers including faults and folds that influence earthquake ground motions. The subsurface target zone is in the 100-to-3000 foot depth range. The anticipated time frame to acquire these data will be about 10 days beginning on or about June 8, 2009.
Motivation and Outline of This Study
A primary objective for the U.S. Geological Survey's National Earthquake Hazard Reduction Program in Nevada is the development of a realistic earthquake-hazard map for the Reno/Carson urban corridor. The Survey expects to spend as much as a million dollars of Federal funds over the next few years to study our urban area. Scientists at the University of Nevada are receiving some small Federal grants to collaborate in these studies. The objective this June for the Geological Survey's field crew is to image potential earthquake faults in the geologic basin underlying Reno and Sparks, and to better characterize the basin itself.
The USGS/UNR survey work will take place from June 8 through 18. Survey work, during daylight hours only, will extend along the River west from Rock Blvd., through downtown, to Keystone Ave. or Booth St.; and also for a few miles along Manzanita Ln. west of Virginia St. They surveys will be full-scale seismic reflection soundings as are done for oil and gas exploration. A seismic vibrator with a 700-lb reaction mass, mounted on a 1-ton pickup will induce seismic waves in the ground. The waves will be recorded by coffee-cup-sized sensors planted in turf or pavement joints on 4-inch spikes. The sensors are connected by about a mile of cable, which will be placed in a cable guard where it must cross traffic. The truck-mounted vibrator will creep about 1 mile per day along the River path, street parking lanes where they can be closed temporarily, and traffic lanes only where necessary. No single location will be obstructed for more than a few hours. The 700-lb vibrator has been tested for years in California and Utah, and only damages pavements very rarely. The USGS and UNR will repair any damage caused by the survey. All survey results will be scientifically vetted and publicly available.
This Federally sponsored work will collect some of the information needed to make the earthquake hazard map. Earthquake-hazard parcel mapping, as is being done now in Clark County, is another crucial component of the hazard map. The U.S. Geological survey has so far been unable to provide funds for parcel mapping anywhere in the country.
General Location of Seismic Profiles
The seismic surveys will take place along two routes
totaling about 7 miles in length: the River profile; and the Mazanita profile.
Attachment 1 on pages 9 and 10 below shows maps of the routes.
Some additional locations will be occupied as well, for
additional recording activities.
The proposed River seismic profile location is shown on the
map as the yellow line with red waypoints. Acquisition along the Truckee River Path will extend west
from Rock Blvd., run along Mill St. between Museum Dr. and Sierra St., along
Island Ave, and then along the River Path to Booth St.
The proposed Manzanita seismic profile location is shown on
the map as the yellow line with red waypoints. Acquisition will extend west from Virginia St. initially
along Redfield Pkwy., to Manzanita Park at Baker Ln., then west along Manzanita
Ln. to West McCarran Blvd.

Figure 1a. Minivibe vibroseis truck operating along street in Santa
Rosa, California, in October, 2007.
Data Acquisition Process – Roadway/Street
Operations
We will use the vibrations generated by a rubber-tired “minivibe” vibroseis truck (Figures 1a and 1b) as the seismic source. This seismic source is preferred in urban situations and on roadways over other traditional seismic sources, such as explosives, because a) the source energy is spread out over about a 12 second interval rather than being released all at once, and b) the source is non-invasive, operating on the ground surface without the need for drilling or excavation. This vibroseis truck will drive along the entire profile route stopping at 15-ft intervals to put a 4-ft diameter polyurethane pad on the ground surface. Part of the truck’s 14,000-lb weight is put on the pad and the pad is vibrated for about 8-12 seconds. This 8-12 second vibration “sweep” is repeated 4-10 times at each stop, then the truck is ready to move up to the next station after about a minute. The audible noise from the vibroseis truck is about the same as a garbage truck operating in a neighborhood.

Figure 1b. Minivibe vibroseis and USGS recording vehicle (1-ton truck with camper) operating along residential street.
![]()


Figure 2. a) Placement of the ground motion sensor (geophone) in the joint between curb and sidewalk. b) Sketch of 5/16”-diameter hole drilled 1” into concrete for geophone placement. Hole will be backfilled with epoxy when completed.
During generation of the seismic signal, ground vibrations may be felt in the vicinity of the truck and up to about 200 feet away at a maximum level of 0.04 in/sec at about 20 Hz. These vibration levels are about 10 times lower than the peak particle velocity damage thresholds set by the U.S. Bureau of Mines (see section (3) “Impacts to pavement and utilities”).
The vibrations generated by the truck are detected and recorded by sensitive “geophones” placed every 15 feet along a cable that stretches for 3/4 mile in front of the vibroseis truck. The geophones are about 4 inches tall with a 2-inch steel spike that is pushed into the soil off the edge of road to firmly couple the sensor to the ground. Where there is only concrete or asphalt, a 5/16”-diameter hole will be drilled 1” deep into the joint between the curb and adjoining pavement (Figure 2). The geophone will be placed in this hole during data acquisition, but then will be removed at night. Holes in concrete or asphalt will be back-filled with caulk/epoxy after use.
As the vibroseis truck moves along, the geophones and cables are also moved up to record ahead of the vibroseis truck. The average speed of the vibrator truck during this data acquisition process is about 0.3 miles/hour. We anticipate that the vibrator truck will be in operation for about 10 days (8 hours/day) between 8 am and 6 pm, along the route. In addition to the vibrator truck, there will be 2 other 3/4-ton pickups, and one 1-ton pickup. Personnel from the USGS will be with the equipment at all times and ready to answer questions from the public and give out information regarding the survey. After the survey is complete there will be little evidence of our work at the site.
2)
Excavation Plan:
Because all
equipment used for this study are non-invasive and mobile, no excavations
are required to complete this work.
3)
Traffic Control:
Figure 3 below shows
our Traffic Control Plan along typical roadway for the vehicles involved in the
USGS seismic imaging study along this route.
Operation of
the vibroseis truck
The vibroseis truck, which is 20-ft long and 7-ft wide, will operate in the parking lane or along the road shoulder while operating along city streets, as shown in Figure 3.

Figure 3. Typical position of the vibroseis truck operating in the parking lane or on the shoulder along SR 147.
In
this position the truck will not be in the traveled way and traffic will flow
freely. The vibroseis truck will work along the
shoulders but may at times be required to partially encroach onto the eastbound
lane. Tall 28” cones, a large flashing
directional arrow board, orange 1-meter square
“Survey Crew Ahead” signs and high-intensity warning
flashers mounted on all vehicles will be used to alert oncoming traffic
of our activity. All USGS and UNR personnel will be
wearing safety orange or green vests or shirts.
Operating the vibroseis truck during data acquisition is a semi-mobile process involving a continuous sequence of 1-minute stops followed by a truck move of 15 feet east along the roadway. To alert motorists and bicyclists in advance of the vibroseis truck work area, the truck will have a flashing yellow double beacon mounted on top, a “slow-moving vehicle” triangle mounted on the back of the vehicle, 4-way flashers, plus headlights, and a bright flashing arrow board (in caution mode) operating at all times mounted on rear of the truck. The “Survey Crew Ahead” warning signs will be placed about 100-200 yards behind and ahead of the vibroseis truck to alert drivers and bicyclists in both directions. Because the operation moves slowly (less than 1 mph), the stationary signing will be periodically retrieved and repositioned in the advance warning area.
Placement of
the cable and sensors
For several hours
before starting the vibroseis truck we will be laying the cable and sensors
along the south edge of the roadway.
To drop the cable along the roadway we will likely use a 3/4-ton white
USGS-marked pickup, equipped with flashing yellow double beacons and strobed
taillights/front turning lamps, moving along in the direction of traffic within
the parking lane or along the road shoulder. Cable laying along portions of
bikeways will employ officially marked 4-wheel ATVs. Cable and sensor
installation is done by 5-8 workers wearing safety orange vests or shirts. To
alert pedestrians and autos to the presence of the cable and sensors at
cross-traffic areas, fluorescent traffic cones will be put down. The cable will also be tucked against
the curb when present so as not to impede pedestrian traffic. When crossing streets, bikeways, or
pedestrian traffic areas, the cable will be covered by a 1-inch-high rubber
guard, which is taped to the pavement.
The rubber guard is taped down at intersections so as not impede the
flow of traffic on the streets or restrict access to businesses and residences.
We expect no damage to any
pavement or underground pipe or structure. We have conducted over 100 miles of these types of surveys
in a variety of urban conditions with over 40,000 vibration points and caused
no damage to above- or below-ground structures or pavement. In fact, when the vibroseis truck
operates on city street pavement, there is no marking, denting, or scratching
of the pavement surface. This
absence of damage suggests completely elastic behavior of the soils and
pavement around the vibroseis source pad.
The vibroseis truck we will use operates on the ground surface and
involves no excavation. In
addition, in contrast to impact or explosive sources, the vibroseis source
energy is spread out over 8-12 seconds thereby decreasing the impact on the
built environment. Buried pipes
and other below-grade structures are constrained by the surrounding soil and move
in the same manner as the surrounding material during a vibration episode. In
contrast, structures located above ground, are relatively free to respond in a
manner different from the ground upon which they are built: they could amplify
or attenuate the input ground motions.
Buried pipelines will withstand vibrations well in excess of the U.S.
Bureau of Mines (USBM) recommendations for above ground structures, and the
expected vibration levels in our study near the vibroseis truck will be well
below the USBM criteria. For example,
in a study of the vibrations from six, 25,000-lb vibroseis trucks operating
simultaneously on Los Angeles streets for several years in the 1970's, there
was only one instance of minor damage to a home and the generated strains
throughout the surveys were far less than those from environmental sources
(Oriard, 1994). We are also aware
of the results of vibroseis operations in the city of Santa Monica, Calif., in
2000. In that case, a single
30,000-lb vibroseis truck operated on city streets for several days without
damage to infrastructure. For this
study we will use only one, 14,000-lb vibrator, so the strains and vibrations
will be far less than those described for the work in Los Angeles. For an additional common-sense measure
of precaution, we will not operate the vibe directly over manhole covers, sewer
grates, or directly over any marked utility line.
Oriard, Lewis L., 1994, Vibroseis operations in an urban environment: Bulletin of the Association of Engineering Geologists, v. 31, no. 3, p. 343-366.
4) U.S. Government Legal Provisions Concerning Liability (Bonding) and “Hold Harmless” agreements:
Because of the peculiar nature
of the United States Government, its employees and agents may act only in the
manner set forth in statutory mandates. As a result, in several instances it is
unable to "contract", or enter agreements in the conventional way.
One such peculiarity is that an agency cannot enter into "hold
harmless", or "indemnity" agreements on behalf of the Government
unless specifically authorized, since such an agreement would seem to amount to
an agreement for an expenditure and/or liability which might arise in the
future. This may be interpreted or construed as a commitment or obligation of
funds prior to appropriation by Congress, which is prohibited by statute. (31
U. S. C. § 665; California Pacific Utilities Co. v. U. S., 194 Ct. Cl.
703 (1971)) Consequently, a substitute provision, set forth below, tailored to
fit the Government's statutory restrictions, provides essentially the same
protection a landowner would seek under a "hold harmless" agreement.
It states that the Government promises to perform the work with all reasonable
diligence and precaution. Failure to do so could be considered a breach of
contract, which could be disposed of under the Tucker Act. (28 U. S. C. §1490)
Also, the Federal Tort Claims Act (28 U. S. C. § 2671) provides a recourse
against the Government for negligent acts or omissions of employees resulting
in injury or damage.
The Survey agrees that the
(construction, installation, maintenance and use) of the (structures,
appurtenances, equipment, and tools) on the lands (of the Landowner, lessee, etc.) on which they are (used or
installed) shall be effected with all reasonable diligence and precaution to
avoid damage to the and, property, or personnel of the (Landowner); further,
the Government agrees to cooperate, to the extent allowed by law, in the
submission of claims pursuant to the Federal Tort Claims Act against the United
States by third parties for personal injury, or property damage resulting from
the negligent act or omission of
any employee of the Government in the course of his employment (28 U. S.
C. §§ 2671, et seq.).
Another aspect peculiar to the
United States, is the question of insurance. Although in a sense the United States has been referred to
as being "self insured", it does not take out or carry liability
insurance, but disposes of its liabilities under the Federal Tort Claims Act.
It has been held that a government agency, absent specific statutory authority,
cannot purchase insurance (19 Comp. Gen.
798). Thus, the United States cannot produce a certificate of insurance
when requested: however, all proper claims will be disposed of under the
Federal Tort Claims Act. In conjunction with this, the Government can require
its contractor, if any, to provide a certificate of insurance to cover the
contractor's activities during the course of a specific project.
What
Is A Tort Claim?
There are two types of Tort
Claims. The first and most common is a tort claim filed against the United
States (SM 451.1.1). These claims involve
property losses, property damage, personal injuries and deaths alleged to have
resulted from the negligent or wrongful acts or omission of employees of the
USGS in the course of their duties. The second type of tort claim is one
filed by the Government (SM 451.3) to
recover for damages to Government property under the USGS jurisdiction.
Who Is Responsible for Assembling/Forwarding Tort Claims
Against the Government?
Usually the responsibility
for assembling and forwarding Tort Claims resides with a member of the
Administrative staff within the District, Field, Team or Center office where
the USGS employee or Government property resides. Although assembling the
claims may be the responsibility of the Administrative staff, employees and
supervisors are responsible for providing certain pieces of information to make
the claim complete.
What Is Required To Forward A Tort Claim Against The
Government?
When dealing with claims
against the Government, the claimant is responsible for initiating the claim,
however, they often need information to get started. It is appropriate for the
USGS to inform claimants that they must submit a complete Standard Form (SF-95)
- Claim for Damage, Injury, or Death to the District, Field, Team or Center
office that is responsible for forwarding the complete claim package. Be
careful during conversations with claimants not to provide an opinion on the
validity of the claim. Once the claimant has submitted the SF-95, the following
information is required before the Tort
Claim can be forwarded for review and processing:
1) A memorandum summarizing
the claim. This memorandum should contain information about the accident or
incident such as the location and date, the name of the USGS employee involved,
and any additional information that may be helpful to the reviewer.
2) The completed SF 95 from
the claimant. Check to insure that the form is complete. This would consist of:
Supporting documentation of
physical injury (medical bills, prognosis, etc.) and/or Property damage (proof
of value of destroyed property and/or two independent estimates for repair or
receipts from actual repair).
If the SF 95 is not
complete, contact the claimant and request the additional information.
3) Submit copies of all USGS investigative reports that are required. This would
include:
Form DI-134 - Report of
Accident/Incident (required for GSA and DOI vehicles)
Standard Form 91 - Motor Vehicle
Accident (GSA vehicles)
Standard Form 91A - Investigative
Report of Motor Vehicle Accident (GSA vehicles)
Standard Form 94 - Statement of
Witness (GSA vehicles)
If the accident involves
water craft or aircraft, refer to Safety and Environmental Handbook, 445-1-H
Chapter 5, Reporting and Record keeping.
4) Submit copies of all
independent investigative reports if available. These may include reports from
the Highway Patrol, City Police, etc.
5) Optional Form 26 (GSA
Form) - Data Bearing Upon Scope of Employment of Motor Vehicle Operator AND a
copy of the Travel Authorization if the employee was in official travel status
at the time.
Where Should Complete Tort Claims Against the Government
Within Central Region Be Submitted?
All Tort Claims that
involve USGS employees within the Central Region, state of Nevada should be
forwarded as follows:
Any claim involving personal
injury or death AND/OR exceeds $2,500 - Forward directly to the Field
Solicitor's Office, 755 Parfet Street, Suite 151, Lakewood, CO 80215.
Any claim with no personal
injury AND is for an amount of $2,500 or less - Forward directly to the Central
Region Service Center address: Chief, Office of Program Support, P.O. Box
25046, Denver, CO 80225.
The items required for a
complete claim do not vary regardless of where the claim will be processed.
Who Pays for Tort Claims Against The Government?
If the total claim is
$2,500 or less, the cost center where the USGS employee is located pays the
claim. If the claim is deemed valid, the claimant receives, signs and returns a
Voucher For Payment (SF 1145) to the Central Region Center office. This voucher
is then sent to the District, Field, or Center Office that forwarded the claim.
The appropriate account code is applied by that office and the voucher is
submitted for payment. Once the voucher has been processed for payment, return
a copy of the voucher (SF-1145) to the Central Region Service Center indicating
payment has been made.
If the claim is more than
$2,500, the claimant receives, signs and returns a Voucher for Payment
(SF-1145) to the Solicitor's Office handling the claim. The Solicitor's Office
then submits the voucher directly to the Department of Treasury, Judgement
Branch.
Who Is Responsible For Completing/Submitting Tort Claims On
Behalf Of The Government?
These claims are referred
to as Government Tort Claims (SM 451.3). The USGS employees responsible for
operation of facilities and equipment under their jurisdiction should exercise
every precaution to prevent accidents. When accidents do occur that justify the
initiation of tort claims in favor of the Government, these claims should be
pursued with the same sense of urgency as the Departmental policy for Tort
claims against the Government (451 DM 1).
Where Should Tort Claims on Behalf Of The Government Be
Submitted?
All Government Tort
Claims within Western Region should be submitted to your respective Regional or
Field Solicitor's Office.
5)
Attachment 1: Location Maps of Proposed Seismic Profiles

The proposed River seismic
profile location is shown on the map as the white line with red waypoints. Acquisition along the Truckee River
Path will extend west from Rock Blvd., run along Mill St. between Museum Dr.
and Sierra St., along Island Ave, and then along the River Path to Booth St.

The proposed Manzanita seismic
profile location is shown on the map as the white line with red waypoints. Acquisition will extend west from
Virginia St. initially along Redfield Pkwy., to Manzanita Park at Baker Ln.,
then west along Manzanita Ln. to West McCarran Blvd.