Quarterly Report to the Harry Reid Center
UCCSN-DOE Cooperative Agreement
Task 12: Seismic Monitoring
PI: James N. Brune
UNR Seismological Laboratory
Report Period: 01/01/2002 – 03/31/2002
Progress:
During this reporting period (Jan.-Mar. 2002), we have maintained
seismic operations under the QA procedures which have been established with the
HRC. Data collection has been above
99.5% overall. Strong-motion stations
(9 TerraTech recorders) were visited, data downloaded, and maintenance
performed. A number of field repairs
were performed in this quarter. Minor
changes have been made in software at the recording lab to improve recording
reliability.
The draft of the FY01 seismicity report was finished in March and
is under internal review. The summary
report on the seismic parameter “kappa” is still in progress.
At the end of this quarter, we have completed analyzing the
earthquakes in the YM vicinity through February 6. Completion of analysis on a delayed basis is acceptable because
the entire set of station triggers is reviewed within 2-3 days and because all
events larger than roughly M 2 are always analyzed within 2-3 days.
All of the five software programs addressed in NCR UNR-01-0027 have been entered into the Software Configuration Management, as Level 3 software. This closes the NCR on this nonconformance.
Instrumentation (seismometers and recorders) has been ordered for
the three tunnel seismic station installations. An instrumentation order for the three wells on the pad of the
proposed Waste Handling Building is nearly finalized. A strong-motion instrument has been relocated
from Solitario Canyon to the ESF pad.
The instrument is in operation.
Approval of the two Death Valley seismic stations was received,
and both stations have been installed.
As of this date, only one (Lees Camp) is sending data because a relay
antenna still must be installed on Rogers Peak in Death Valley National Park
for the other station.
The project to transcribe raw digital seismic data previously
submitted to the RPC on 4-mm tapes to DVD media has been completed, resulting
in 179 DVD’s. Transcription of the
older data depends on vendor completion of purchase orders to move data from old
9-track tapes to 4-mm tapes. About 120
such 9-track tapes have been processed, and the 4-mm data has been moved to
hard disk.
We coordinated with Los Alamos Labs on selecting two seismograph
sites in the ESF. The stations will be
broadcast on the fiber to a central data management computer in the Los Alamos
data shack. Timing issues related to transmitting acceptable GPS signal along
the fiber have been solved and will be implemented for the ESF stations.
We met with Harry Reid Center hydrologists to discuss the
prospects of incorporating well monitoring data into the real-time telemetry
system operated by UNR. We also met
with LLNL and UNLV engineers in planning for a potential micro-earthquake
deployment near the ESF. This is
intended to establish base-line data for ESF performance related issues.
Problems:
We have arranged, after lengthy preparations, to have our
technicians travel under escort on NAFB the week of April 8-12. Under Task 12, we have two stations to
maintain on NAFB. The current
arrangement is hardly workable in the case that one of these stations goes down
and needs repair or in the case that we wanted to deploy instruments on NAFB
after a significant earthquake in the Yucca Mountain vicinity. We would like to have the time between our
recognizing a need to travel on NAFB and the actual trip be just a few hours in
the case of monitoring aftershocks.
Status of Funds:
As of the end of March, we are roughly 20% behind in our spending
on the contract, based on a uniform level of expenditures throughout the
year. Significant equipment orders are
soon to be placed, bringing that category up.
Plans:
We will continue work on the compendium report of NSL work on the
seismic parameter kappa. Actual
delivery time depends on the downstream schedules for other YMP participants.
We will submit the completed set of DVD’s to the Records
Processing Center for the 1995-2001 refraw data. We will begin the transfer of the older
analog network data to DVD’s this quarter.
We will take delivery on equipment to be installed in the tunnel
and on the pad and complete bench testing of it in this quarter.
We will send out the FY01 seismicity report in this next quarter for formal review. Due to the relatively low level of seismic activity within the monitoring network for FY01 and the fact that the report covers very little new material, we anticipate submitting a final before the end of this next quarter.